wetlands, housing and commercial space to an area that was formerly home to
heavy industry.
“This is very exciting and we’ve been waiting for this for a long time,”
said Toronto-Danforth Councillor Paula Fletcher after the ceremonies held on
a barren, wind-swept plot of concrete-covered land south of Commissioners
Street, between Cherry Street and the Don Roadway.
By 2024, it’s expected that the site will be unrecognizable from what it is
today as the course of the Don River will be basically dug through a
one-kilometre portion of the site, creating a river valley, wetlands at the
mouth of the river and a new island to be known as Villiers Island that will
provide housing and economic opportunities for thousands.
Officials from the federal government, the City of Toronto, Waterfront
Toronto, and the Mississaugas of New Credit First Nation were on-hand for
the Nov. 28 groundbreaking of the $1.25-billion project. Notably absent were
any representatives of the provincial government.
“I’m disappointed the Ontario government did not come,” said Fletcher.
“They are an important part of this.”
Funding for the project is split three ways between the federal, provincial
and city government – with each committing more than $416 million.
While flood protection is a critical portion of the project, so are the
housing, employment and recreational portions.
“This is 75 acres of parkland by the river with recreational trails and
natural areas,” said Fletcher. “It’s also 25 acres of housing, and 30 per
cent of that has to be affordable housing. It will be a benefit to our city
over a long number of years.”
The flood protection project launched Wednesday is all part of the massive
revitalization plan for Toronto’s eastern waterfront, and it will be one of
the largest construction projects presently taking place in North America.
It is expected to be completed by 2024.
Some 1.4 million cubic metres of soil and fill will be dug up as part of
the project, that’s approximately 180,000 dump trucks worth. To create the
wetlands and new shoreline at the mouth of the Don’s new course will require
more than 195,000 cubic metres of clean fill and another 182,000 metric tons
of locally sourced aggregates. Also, more than 1.2 million seeds will be
planted to create new habitats along the river valley.
Construction work actually began in July of this year with the clearing of
the land between the Keating Channel and the Ship Channel in preparation for
the digging of the new river course which starts this winter.
The official preparation for this project goes back more than 10 years,
Fletcher said, with the start of the Environmental Assessment process in
2007.
However, the inspiration for revitalizing the mouth of the Don River and
the Port Lands area goes back decades, she added.
“This goes all the way back to 1986 and Bring Back The Don. The focus is on
the river and the river is at the centre of this and it is going back to a
more natural course.”
For more details on the Port Lands Flood Protection Project, please visitwww.portlandsto.ca