by late September 2011.
All work of this project will take place on City property. Additionally, during
the duration of the work, parking lanes will be occupied by Toronto Hydro
workers which will reduce traffic to single lanes in each direction. They will
do their best to minimize inconveniences during the construction. Below is the
letter Toronto Hydro is sending to residents of the affected area.
_______________________________________________________________________________
To our valued customer:
Re: IMPORTANT NOTICE – Underground Construction- Project Dundas-
Greenwood
Toronto Hydro is in the process of upgrading the electrical system on your
street.
We are planning to construct underground ducts, switching vaults & cable
chambers.
The affected streets of this project are Alton Avenue, Badgerow Avenue, Curzom
Street, Dagmar Avenue, Dundas Street East, Gerrard Street, Greenwood Avenue,
Hiltz Avenue, Jones Avenue, Leslie Street, Mallon Avenue and Pape Avenue.
The construction will begin mid January 2011 and is tentative to be completed
by late September 2011.
All work of this project will take place on City property. Additionally, during
the duration of our work, parking lanes will be occupied by our workers which
will reduce traffic to single lanes in each direction. We will do our best to
minimize inconveniences during the construction. The scope of work includes open
trenching, tunnel excavation and installation of well points to control ground
water in order to install cable chambers, switching vaults and conduits to
maintain a reliable level of service to you and your neighbours. The planned
work for this project does not anticipate any power interruptions. Entera
Utility Contractors and Toronto Hydro Inspectors will be on-site throughout the
course of this project. We encourage you to discuss any concerns you may have
with them directly. Please be informed that work is scheduled for both weekdays
and weekends. Restoration will be done in various stages during construction of
the project. All asphalt between cutlines will be replaced if affected by our
excavation. After Hydro’s construction, the City will make permanent asphaltic
concrete repairs. Thank you in advance for your cooperation and understanding in
this matter. We apologize for any inconvenience and recommend customers to
exercise caution around construction areas. Should you require additional
information, please contact Christopher Chahine at 416-542-3366 or
[email protected]
and reference
PROJECT DUNDAS- GREENWOOD. For further information on the PowerUp initiative, please visit our website at
http://poweruptoronto.ca. Sincerely,
Christopher Chahine Customer Operations