PARKMOUNT PARKING LOT UPDATE

The final design for the TPA lot at Parkmount and Danforth was approved at the last community council. The new surface parking lot will be properly graded, contain 18 parking spaces (including 1 handicapped space), as well as include a green bioswale and landscaped areas along the street perimeter. I have included the design so you can get a better idea of what it will look like when
completed.

The work is to begin May 2nd, 2011 weeks and should be completed by mid June, 2011. During that time the parking lot will not be accessible. For further information please contact Remy Iamonaco, Project Engineer with Toronto Parking Authority, by phone at 416-393-7335 or by email at [email protected] Thank you for your patience.  I always look forward to hearing from you – your ideas, suggestions and concerns on this or any other matter.