THE LOCAL PROJECT
Starting on Sunday April 15, 2018, overnight track work began on the Lakeshore East rail corridor between the Don Valley Parkway and Gerrard Street East. Below is an updated schedule of the overnight work:
April 15 - April 19, 2018
Track work will take place between Eastern Ave. and Carlaw Ave.
April 20 - April 22, 2018
Track work will take place between the Don River and Dundas St. E This work requires the use of excavators, hydraulic and hand tools, equipment and trucks with audible back-up beepers. We do as much as possible to minimize the effects of the construction on our neighbours. However, this work will create some noise from trucks, moving of materials and equipment, and some ambient light from the work site.
TIMING
Work will take place between 10:00 p.m. and 5:00 a.m. for approximately four weeks.
QUESTIONS
For more information, feel free to contact Jody Robinson, Community Relations and Issues Specialist, Lakeshore East Corridor Tel: 416-202-7210 / E-mail: [email protected]
Click here for the notice